*Project |
The heavy haulage route from Tutunup South to the Capel processing plant includes the southern end of Ludlow Hithergreen Road, Vasse Highway, Sues Road and onto the Bussell Highway.
Infrastructure will include the establishment of an open cut mine, screen plant, concentrator, workshops, fuel storage areas, solar drying dams, a process water dam, offices and pipelines.
Hours of operation for earthmoving equipment 7am to 7pm 6 days a week (Sundays off), hours of operation for concentrator 24 hours a day, 7 days a week.
|